Excavation & Dirt Removal Calculator

Calculate excavation volume in cubic yards, the hauled (loose) volume after soil swell, and the number of dump-truck loads to remove it. For footings, foundations, pools, ponds, and grading.

Typical: 10-16 cu yd tandem; 12-18 tri-axle.

In-place (bank)

29.6

cu yd

Hauled (loose)

37.0

cu yd after swell

Truck loads

4

@ 10 cu yd

Cubic feet

800

in-place

Did this help?

How to Use This Calculator

Enter the length, width, and average depth of the excavation in feet. Choose the soil type — excavated soil 'swells' and takes up more space than in-place ('bank') soil, so the hauled volume is larger. Set your dump truck capacity to get the number of loads to haul off.

Formula Used

Bank volume (cu yd) = L × W × D ÷ 27. Loose/hauled volume = Bank volume × swell factor (sand 1.12, loam 1.25, clay 1.30, rock 1.50). Truck loads = Loose volume ÷ truck capacity, rounded up.

Free Software Guide for General Contracting Professionals

Get our free guide comparing the best software tools for general contracting businesses — with real pricing and honest recommendations.

No spam. Unsubscribe anytime.

Disclaimer

This calculator is for estimation purposes only. Results may vary based on local conditions, materials, and building codes. Always consult a licensed professional before making decisions based on these calculations. MyContractorTools is not responsible for any errors or omissions.